EMT Practice Test

1. Question Content...


Question List

Question1: Which of the following is a typical characteristic of Scrum?

Question2: A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Question3: A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Question4: A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:


Which of the following most likely represents the number of items in the backlog?

Question5: Which of the following is a capital expense?

Question6: While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

Question7: After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?

Question8: Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

Question9: Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?

Question10: During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Question11: A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the followingdocuments should the project manager produce FIRST to start communication about the boundaries of the project?

Question12: A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Question13: During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

Question14: During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

Question15: A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?

Question16: During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
* Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
* Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:

Part 2:

Question17: A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

Question18: Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Question19: During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Question20: Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

Question21: A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?

Question22: A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

Question23: Which of the following tools is best to use when conducting project meetings across time zones?

Question24: A project manager, who finished a project some time ago, keeps receiving questions from another project manager who is currently leading a similar project. Which of the following is the most likely cause of this situation?

Question25: Which of the following tools is best to use for storing lessons learned?

Question26: When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Question27: Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

Question28: An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

Question29: During the testing phase of a project, the regression test fails due to a specific item that is disrupting the entire system. Which of the following documents should the project manager use to identify who requested this item?

Question30: While working in a collaborative, online brainstorming session, team members send private messages to the facilitator about challenges understanding others when they are speaking due to accents and background noises. Which of the following should the facilitator do to overcome the challenges?

Question31: Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Question32: A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Question33: In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?

Question34: After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Question35: While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

Question36: During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Question37: Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Question38: Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Question39: A project manager is overseeing the implementation of a major upgrade to a critical ERP system. The project sponsor is requiring that the upgrade should not exceed more than three hours of downtime for the implementation and validation in production. During cutover, the team runs into a validation issue after 2.5 hours, and the process is only 70% through the validation steps Which of the following actions should the project manager take?

Question40: A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

Which of the following is the current status of the process?

Question41: Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Question42: During a kickoff call, a project was rejected by the legal department due to the risk of violating new legislation. Which of the following was applied?

Question43: An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

Question44: In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Question45: A project manager needs to update the project sponsor and senior stakeholders about the progress of a project.
Which of the following tools will the project manager MOST likely use?

Question46: A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Question47: An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

Question48: A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

Question49: A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Question50: Which of the following provides the best justification for undertaking a project?

Question51: Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect.
Which of the following actions should the project manager take NEXT?

Question52: As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Question53: A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Question54: Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

Question55: A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

Question56: While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

Question57: During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

Question58: A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
* Two developers
* High uncertainty about existing systems
* Risk of frequent requirement changes
* Tight deadlines
Which of the following project methodologies would be best to use in this situation?

Question59: A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

Question60: Which of the following BEST illustrates how team members with different roles should interact on the team?

Question61: A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Question62: During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?

Question63: A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Question64: A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

Question65: Which of the following is the main reason for documenting artifacts?

Question66: Which of the following would be considered operational security?

Question67: During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase.
Which of the following documents is the best source for the PM to use to confirm this assertion?

Question68: Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Question69: A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

Question70: By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

Question71: Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Question72: A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Question73: A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Question74: During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Question75: A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

Question76: A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

Question77: A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Question78: Which of the following statements best describes a content management system?

Question79: During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Question80: Given the following information:

Which of the following represents the critical path of the project?

Question81: A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?